Major construction projects have returned to the landscape of Jacksonville's urban core. Find out where (and more) as we take a brief look at the status of various developments under construction in and around Downtown Jacksonville during the month of February.

Downtown




1. Parador Parking Garage


Future retail build-out if the adjacent Suntrust Tower reaches 65% occupancy.

Vertical construction continues on the Parador parking garage project, at the intersection of Bay and Hogan Streets. The six-story, $10 million structure will contain 607 parking spaces. Street level retail will be added once the adjacent Suntrust Tower reaches 65% occupancy.










2.Palmetto Place

Construction is nearing completion on the addition of assisted living dorms at 450 Palmetto Street.







3. Southbank Riverwalk



The Southbank Riverwalk's grand opening is today, February 26, 2015.









For more information: http://www.coj.net/departments/public-affairs/headlines/new-southbank-riverwalk-construction-to-begin.aspx




4. Jessie Ball duPont Center



Construction on the $20 million Jessie Ball duPont Center continues to move forward. When complete in early 2015, the Jessie Ball duPont Center will serve as the epicenter for Northeast Florida's philanthropic and nonprofit community. The 120,000 square foot building will act as a hub for local nonprofits, stimulating an environment of collaboration within the sector. Additionally, the four-level facility will include retail, conference/meeting spaces, a green roof, and an outdoor patio/terrace area at the intersection of Ocean and Adams Streets.



For more information: http://www.metrojacksonville.com/article/2013-dec-jessie-ball-dupont-center-haydon-burns-renderings



5. Beaver Street Villas



LaVilla's long closed New Center Hotel at 605 North Broad Street is being renovated by nearby Clara White Mission into street level offices and 16 upper level apartment units.



For more information: http://www.metrojacksonville.com/article/2013-jul-more-downtown-mixed-use-beaver-street-villas




6. State Attorney's Office

Work continues on the $26 million reconstruction of the old courthouse as a new home for the State Attorney's Office. Construction is estimated to be completed in early 2015.











7. New York Steam Laundry Building


Proposed Building Façade

Interior demolition on the redevelopment of the New York Steam Laundry Building is complete. L.B. Jax Development, LLC. plans to convert the 11,000 square foot historic structure into restaurant and office space.



For more information: http://www.metrojacksonville.com/article/2014-feb-new-york-steam-laundry-development-project-renderings



8. Levels

Former New York Jets wide receiver Laveranues Coles Jr.'s plans to convert 323-325 East Bay Street into a three-story restaurant called Levels is underway. Described as an "upscale and grown venue," each floor will feature a bar and stage for live music.







9. Super Food & Brew

Buildout is underway at Super Food Truck's new brick & mortar restaurant at the 11 East Forsyth Building. The restaurant is expected to open in Spring 2015.